Task 1: Project Coordination (11/18 - 10/19)

Task 2: Identification of Potential Flood Improvement Projects (11/18 - 3/19)

Task 3: Regional Model Development (11/18 - 4/19)

Task 4: Modeling of Flood Mitigation Projects (3/19 - 7/19)

Task 5: Surveying (2/19 - 6/19)

Task 6: Agency Coordination (11/18)

Task 7: Project Evaluation Reports (7/19 - 9/19)

Task 8: Priority Matrix (8/19 - 10/19)

Task 9: Public Involvement (11/18 - 10/19)

Task 10: Build Out Analysis (6/19 - 9/19)

Task 11: Basin Storage/Discharge Analysis (9/19 - 10/19)

Task 12: Summary Report (9/19 - 10/19)

Schedule