Executive Summary 7/27/2010

Project objective: To restore historic hydraulic flows and extend the hydroperiod at the Daniels Preserve @ Spanish Creek (Conservation 2020 preserve).

 

Spanish Creek Location Map

Spanish Creek Timber Bridge Analysis 

Spanish Creek Survey

Preliminary Synopsis

April 2013 Meeting Minutes


Expected Completion Date: 2014

Project Status:  Feasibility study expected to be complete in 2008.  Field survey work in progress. Construction expected to be completed in 2009.


Proposed budget: $580,000

Contact information:  Anura Karuna-Muni,P.E., Project Mgr., Phone: 239-533-8131; E-mail: akaruna-muni@leegov.com