The Villas

Learn more about flood mitigation work in The Villas here.


 Flood Assessment Reports

Lee County is pleased to announce the Phase 2 Initial Flooding Assessment Project reports are done and available to the public. Here you will find the PowerPoint presentation that staff prepared for the March 6, 2018, Lee Board of County Commissioners' work session, an executive summary of the reports, maps depicting assessment observations, and the reports with their backup data.

 Presentation to Commissioners (3/6/18)

Executive Summary

Lee County experienced two major rainfall events during the summer of 2017, the events being spaced at an approximated two weeks apart. A major event occurred between August 25 through 27, first known as Invest 92L by the National Hurricane Center (NHC) with many areas in south Lee County getting 10 to 12 inches or more of rainfall in a three-day period, with smaller pockets having higher amounts. Hurricane Irma followed on September 10, which delivered another 6 to 10 inches in most county areas in one day with higher amounts in the eastern portion of Lee County, according to NEXRAD and local rainfall data. The back-to-back events within two weeks did not allow sufficient time for most areas to recover from the late August storm, nor to allow sufficient time for clean-up operations to be completed. Subsequently, the Irma event produced higher flood-water levels in many areas than did the late August event due to the already saturated conditions.  More...

Reports​

 Lehigh Acres Report

 North Fort Myers Report

 Southeast Lee County Report

 South Fort Myers Report

 Whiskey Creek Report

Maps

 ​Lehigh Acres Flood Assessment Rank Map

 North Fort Myers Flood Assessment Rank Map

 Southeast Lee County Flood Assessment Rank Map

 South Fort Myers Flood Assessment Rank Map

 Whiskey Creek Flood Assessment Rank Map


flood.png Flooding Information

For questions about the assessment reports or to Report drainage problems or debris in canals and waterways, contact us online or by phone at 239-533-9400

Flooding Information


 Island Park / The Forest Area Map


info.png Flooding Email Communication Updates

Update #12 - Flood Mitigation Status Update. (June 19, 2018) 

Update #11 - Important information and tips for hurricane season. (June 6, 2018) 

Update #10 - Work continues to ensure flood-prone areas are ready for rainy season. (May 11, 2018)

Update #9 - Flood Mitigation update, Ten Mile Canal, Island Park, The Villas, San Carlos Park (April 4, 2018)

Update #8 - Phase 2 Initial Flood Assessment Project Reports are now available. (March 6, 2018)

Update #7 - Update on San Carlos, Island Park and initial flooding assessment project. (February 1, 2018)

Update #6 - Update on initial flooding assessments and San Carlos Park area (January 10, 2018)

Update #5 - Update on Lee County's flood mitigation efforts post-Hurricane Irma (November 20, 2017)

Update #4 - Lee County continues its flood mitigation efforts post-Hurricane Irma (December 13, 2017)

Update #3 - Information on Lee County's flood mitigation efforts post-Hurricane Irma (December 6, 2017)

Update #2 - Flood mitigation efforts post-Hurricane Irma (November 29, 2017)

Update #1 - Hurricane Irma and flooding issues (November 21, 2017)


Overview

The County experienced two historic rainstorms in 2017 between the dates of August 25 and September 10. While these two storm events covered a great deal of the County, some areas received more than 20 inches of rain during this short period of time. Rainfall at this intense level coupled with Hurricane Irma’s storm surge exceeded the carrying capacity of our natural and manmade drainage features. Consequently, the County is working on its stormwater system using the multi-faceted approach explained below.


Phase 1: Clearing Bodies of Water

The county immediately identified and removed trees and other debris from waterways that were potentially impeding flow and contributing to flooding. This work continues based on field reports. Estimated completion of the first pass of phase 1 is mid-December. Additional passes may be required.



Phase 2: Initial Flooding Assessment Projects

The county is in the process of identifying causes and contributing factors to the recent flooding and looking at what can be done to improve drainage on a relatively short-term basis.  Local consultants are in the field identifying blocked pipes, culverts, ditches, canals, creeks and streams for clearing. They are also reviewing development permits to determine if they are causing or contributing to the flooding problem. Data from this effort will enable the county to proceed with early activities that will provide relief prior to next rainy season. All this information will be documented on an interactive website where the public can track progress and participate and share their observations. Estimated completion of initial assessments is the first quarter of 2018.

Initial Flooding Assessments Map

This map depicts the study areas for the initial flood evaluation. Specifically, the outlined areas are the watersheds that caused or contributed to neighborhood flooding during the rainfall events of August 25-27 and Hurricane Irma. The different colors indicate the consultant chosen to conduct the work. Individual neighborhoods that experienced flooding are not shown.

Click on the map below to load an interactive map with data collected from the initial flood assessments.

Post Storm Flood Analysis - Phase 1 Areas of Investigation Otober 17, 2017
Initial Flooding Assessments Map
Initial Flooding Assessment Map

The County experienced two historic rainstorms in 2017 between the dates of August 25 and September 10. While these two storm events covered a great deal of the County, some areas received more than 20 inches of rain during this short period of time. Rainfall at this intense level coupled with Hurricane Irma’s storm surge exceeded the carrying capacity of our natural and manmade drainage features. Consequently, the County is working on its stormwater system using the multi-faceted approach explained below.

Phase 1: Clearing Bodies of Water

The county immediately identified and removed trees and other debris from waterways that were potentially impeding flow and contributing to flooding. This work continues based on field reports. Estimated completion of the first pass of phase 1 is mid-December. Additional passes may be required.

Phase 2: Initial Flooding Assessment Projects

The county is in the process of identifying causes and contributing factors to the recent flooding and looking at what can be done to improve drainage on a relatively short-term basis. Local consultants are in the field identifying blocked pipes, culverts, ditches, canals, creeks and streams for clearing. They are also reviewing development permits to determine if they are causing or contributing to the flooding problem. Data from this effort will enable the county to proceed with early activities that will provide relief prior to next rainy season. All this information will be documented on an interactive website where the public can track progress and participate and share their observations. Estimated completion of initial assessments is January 2018.

Phase 3: Flooding Long Term Recovery

The goal is to establish a plan to reduce flooding on a larger regional scale. It is important to understand that water management in our area is a complex system and has to be addressed holistically. What you do in one part of the system or watershed can have unintended consequences elsewhere. To consider larger projects such as dredging, diking, diverting, berming or storing water, a series of tools are used to evaluate projects to ensure the project would perform as intended. Those with the most promise are then selected for budgeting and implementation. This next step includes grant applications, land acquisition (if necessary), permitting, design, bid and construction. We expect to present options to the board in late 2018.

Click OK to open the interactive map showing the progress of Phase 2.


Phase 3: Flooding Long Term Recovery

The goal is to establish a plan to reduce flooding on a larger regional scale. It is important to understand that water management in our area is a complex system and has to be addressed holistically. What you do in one part of the system or watershed can have unintended consequences elsewhere. To consider larger projects such as dredging, diking, diverting, berming or storing water, a series of tools are used to evaluate projects to ensure the project would perform as intended.  Those with the most promise are then selected for budgeting and implementation. This next step includes grant applications, land acquisition (if necessary), permitting, design, bid and construction. We expect to present options to the board in late 2018.